Procedures such as building certification

Building certification

The master of building submits confirmation application to chief architect or designated confirmation inspection engine and receives confirmation and must receive grant of comfirmed proof. (it may not be necessary by scales.) 
 
◆Prior consultation relations
・In the case of confirmation application of exclusive housing by "Hiratsuka-shi, confirmation application prior check sheet" with each section concerned
 You perform prior consultation, and please receive confirmation mark.
・In the case of confirmation application except exclusive house, prior consultation by "the Hiratsuka-shi town development regulations" is necessary.
 (please refer to Development Guidance Division in detail.)
・Narrow matches, and please discuss in engineering works General Administration Division when road discussion is necessary.
・When cityscape discussion is necessary, please discuss in town development policy section.
・About permission relations of Kanagawa, please discuss with each department in charge of Hiratsuka, Kanagawa engineering works office.
・Before buildings such as exclusive houses on the third floor or above or more than 10m in height give building certification application; "building certification
 Please do presentation of notification form affecting application.
・Before building in city planning area gives building certification application; "report of act in city planning area
 Please do presentation of book.
 
 
◆Application relations
・The presentation number of copies of confirmation application is original, copy, Part 3 of copy (for firefighting).
・By permission and discussion relations permit (authorization) when have been discussed, and proof is published, attach the reproduction by all means
 Please give.
・We would like application of building certification by from 8:30 a.m. to 4:30 p.m. on weekdays.

Downloading of style in prior consultation relations to page of application style

About application processing fee to page of list of application processing fees

Intermediate inspection

You must apply for inspection within four days from the day when specific process that we appointed was finished about building which Hiratsuka-shi appointed.

Inspection day is principle, Tuesday and Friday. In addition, we do not reserve inspection with telephone.

 
・We would like time in of inspection by from 8:30 a.m. to 4:30 p.m. on weekdays.
・When change occurs before inspection, perform predetermined procedure after meeting with the person in charge beforehand by all means
 Please do.

Specifically, about Hiratsuka-shi intermediate inspection system [PDF]

About public announcement sentence of matter about designation of specific process of intermediate inspection to page of public announcement sentence [PDF]

About application processing fee to page of list of application processing fees

Examination of completion

You must apply for inspection within four days from the day when construction was completed about building which did building certification.

・Inspection day is principle, Tuesday and Friday. In addition, we do not reserve inspection with telephone.
・We would like time in of inspection by from 8:30 a.m. to 4:30 p.m. on weekdays.
・When change occurs before inspection, perform predetermined procedure after meeting with the person in charge beforehand by all means
 Please do.

About application processing fee to page of list of application processing fees

Questionnaire about this page

Was information of this page useful?

Was it easy to find information of this page?

Inquiry about this page

Building Guidance Division

〒254-8686 9-1, Sengencho, Hiratsuka-shi, Kanagawa main building the sixth floor

 Fax number: 0463-21-9769

Direct telephone call number: 0463-21-9731 (building instruction charge) /0463-21-9732 (building responsible for examination / building security charge)

To inquiry form

Go to the top of this page